Footings are next

                                           Carry the rebar down into the hole.
 Layout the rebar, bend and overlap it at least 40 times the diameter of the bar.

                                              Install spreaders and forms to accept the concrete
                                                   Get a little help from our friends.
Install the vertical bars before the concrete sets up.  Timing is everything when dealing with concrete.  NOTE: These footings were inspected by a Lehi City Inspector and we passed...first time!!